APPLICATION STATUS:
- File Status
- File Status
- File Details
900/SEIAA/EC1/3461/2015
| Name & Address of Applicant | Sri. A.G. Madhavan, Managing Director, M/s Nila Metals Pvt. Ltd., Vellappara P.O., Pazhayannur Village, Thalappilly Taluk, Trissur, Kerala-680587 Ph: 04884-229191, Mob: 09847023655 E-mail: thenilasnand@gmail.com |
| Details of the Project | Environmental Clearance for the quarry project in Survey No. 1853/1, 1854, 1855, 1856, 1857, 1858, 1860/1 of Pazhayannur Village, Thalappilly Taluk, Thrissur District, Keralaby Sri. A. G. Madhavan, Managing Director, M/s Nila Metals Pvt. Ltd. |
| File Status | E.C Issued |
| Date of Receipt | 24-08-2015 |
| EC Issued Date | 16-10-2016 |
| Category | Quarry |
| District | thrissur |
| SEAC | 55, 120, 123, 124th |
| SEIAA | 54,60, 112 |
| Reason for Pendency | |
| Remarks |
The 120th SEAC considered the proposal for revalidation as per the Judgment dated.02.11.2020 in WP(C) No.17533/2020 and 23 other cases. The
Committee discussed and accepted the additional details submitted by the
proponent. The Committee entrusted Dr.S.Sreekumar &
Dr.P.S.Easa with the field inspection. The 123rd SEAC Meeting Committee discussed the Field Inspection Report in this regard and decided to defer the item for scrutiny of physical files. The 124th SEAC Meeting Committee scrutinised the files in this regard and decided to recommend to the SEIAA to direct the proponent to comply with some conditions within six months and on satisfactory submission of the compliance report of the above, the proponent will be eligible for revalidation of EC order with the project life of nine years from the date of issuance of the first EC order subject to review every five years. The 112th SEIAA Meeting Authority decided to consider the EC revalidation proposal recommended by SEAC. |